Perrotto Builders, Ltd., Appellant v. Reading School District and Lobar, Inc., 108 A.3d 175


Summary

HOLDINGS: [1]-The trial court properly denied appellant's motion for a preliminary injunction to stop the implementation of a construction contract to renovate school buildings, because appellant was unlikely to prevail on its claim that the school district violated the bidding documents after the bidding was closed by removing school buildings from the project to protect its budget, since the documents gave the district that option.